Power and Utilities
Power and Utilities

Strategic sourcing saving $50M annually for a nuclear plant

Location
Ontario, Canada
Year
2025
Engagement
Profitability Improvement: Sourcing & Procurement
The problem

In 2025, one of the world's largest nuclear power plants sought to reduce its maintenance work backlog by streamlining supply chain lead times. Previous work to reduce over-specification was successful and broader process redesign was required.

Our approach

Our team conducted analyses of contract coverage, price histories, contracting process, and compliance to contracted price. We led the team to re-prioritize contracts to pursue, enabled them with better tools to negotiate lower prices or other value aspects, and ensured compliance to contracted prices through buyer and supplier management scorecards.

Case study figure

Measurable impact

$50M

Achieved $50M CAD in savings annually through multiple levers

Power and Utilities

Case snapshot

Shortened supply chain lead times to support timely maintenance execution

Power and Utilities

Case snapshot

Improved cross-functional collaboration and process efficiency

Power and Utilities

Get in touch

Ready to find out what's driving the gap?

Leave your details and we'll be in touch within one business day.

Or visit the full contact page

* Required fields